30 June 2025
Tower 2
- The excavation work has been fully completed.
- Column work from basement 1 to ground floor is 77% completed.
- Slab and beam work at the ground floor level is 29% completed.
- The next milestone is to begin column work up to the first floor.
Excavation Work - 100% Completed
B1 to GF Level Columns - 77% Completed
GF Level Slab/Beam - 29% Completed
Next Milestone - GF to 1st Floor Column work